2016

Mendoza

Electrical work at El Portón Field

Construction of high-voltage and low-voltage aerial cable; shield wire Optical Ground Wire (OPGW); build of Transformer Substation and switching stations in the Southern area of Mendoza.

2016

Neuquén

EPEN electric infrastructure operation and maintenance – 2016 term.

Operation and Maintenance of the electrical infrastructure system of the province, which is integrated into a network of more than 434.96 (700 km) of 132 kV lines and more than a dozen of Transformer Stations with voltages of 132 kV, 66 kV and 33 kV belonging to the Ente Provincial de Energía del Neuquén.

2016

Mendoza

Maintenance of electric island automation

Operation and Maintenance of bus bars; coupler bay between current busbars and Luján new Transformer Station; coupler bay between current AA busbars; Luján de Cuyo new electric island; control and communication systems that are owned by the carrier; Operation and Maintenance of high-voltage line bays.