2018

Neuquén

EPEN Electric infrastructure operation and maintenance – 2018/2022 term

Operation and Maintenance of the electrical infrastructure system of the province, which is integrated into a network of more than 434.96 (700 km) of 132 kV lines and more than a dozen of Transformer Stations with voltages of 132 kV, 66 kV and 33 kV belonging to the Ente Provincial de Energía del Neuquén. Project was executed in 90 days.

2018

Mendoza

Luján de Cuyo 132 kV Transformer Station extension

EPC Contract- Civil engineering, electromechanical and electrical works. Provision of equipment for medium voltage and communication systems and automation systems, and fiber optic. Building, electro-mechanical assembly and commissioning. Civil engineering works and 13.2 kV underground wiring.

2018

Mendoza

132 kV Electrical Maintenance at Electrical Substation No. 100-CILC

Two-year-contract for electrical facilities maintenance; and high-voltage maintenance at 132 kV Electrical Substation No. 100, located at Luján de Cuyo Industrial Park. On-call duties; preventive and corrective maintenance; underground wire maintenance, among other complementary works related to medium and high-voltage.

2020

Puchuncaví

110 /33 kV Puchuncaví Electrical Substation and 2 x 110 kV high-voltage line

Turnkey contract for engineering, supply, construction, and commissioning of 110 / 33 kV Pacífico Substation, and of 2 x 110 kV high-voltage line, and line opening of 2 x 110 kV at current Ventanas Torquemada.

2020

San Clemente

66/13.2 KV, 20 MVA San Clemente Electrical Substation extension

Single busbar arrangement of 66 kV. 66 kV bay modification; transformer installation of 66/13.2kV 20MVA. Adding two new feeders to 13.8 kV. Complementary work related to electrical room extension.

2020

Lihueimo

66/13.8 kV, 15 MVA Lihueimo Electrical Substation extension

Single busbar arrangement of 66 kV; provision of 66 kV T2 transformer bay, 66/13.8 kV,15 MVA transformer replacement. New bus-bar for feeder No. 4 at 13.8 kV, and new bus coupler.

2020

Loreto

66/15 kV, 20 MVA Loreto Electrical Substation extension

Double bus arrangement of 154 kV, and transfer bus. In 154 kV bay, extension of main bus bar 1 and 2; transfer bus extension; construction of bays A3 and A4; line switchgear bays (transformer switchgear bay, coupler bay), and transformer 154/66/14.8 kV 75 MVA. Transfer bus in 66 kV bay.

2020

Fátima

154/66/14.8 kV, 75 MVA Fátima Electrical Substation extension

Double bus arrangement of 154 kV, and transfer bus. In 154 kV bay, extension of main bus bar 1 and 2; transfer bus extension; construction of bays A3 and A4; line switchgear bays (transformer switchgear bay, coupler bay), and transformer 154/66/14,8 kV 75 MVA. Transfer bus in 66 kV bay.

2020

Mandinga

66/13.8 kV, 15 MVA Mandinga Electrical Substation extension

In 66 kV bay, 66/13.8 kV 15 MVA transformer replacement. In 13.8 kV bay, 13.8 kV switchgear area extension, and construction of 2 feeders. Complementary work related to new electrical room construction, and transformer replacement of auxiliary transformer.